Daihatsu Motor announced on February 16, 2024, that it would lift the shipment suspension order for three models (excluding hybrids) of Toyota Raize, Daihatsu Rocky, and Subaru Rex, after the Ministry of Land, Infrastructure, Transport and Tourism confirmed through witness testing and other tests that they comply with the standards of the Road Transport Vehicle Act . On February 28, 2024, the company announced that it had decided to resume production of the three models (excluding hybrids) of Toyota Raize, Daihatsu Rocky, and Subaru Rex from Monday, March 18, 2024 ( shipments of unshipped vehicles will resume from Monday, March 4) .
Daihatsu Motor Factory Operation Status
| Factory Name | Operation status |
|---|---|
| Shiga (Ryuo) Factory District 2 | [Daihatsu Rocky (gasoline vehicle) / Toyota Raize (gasoline vehicle) / SUBARU Rex] Production will resume from March 18, 2024 ( shipment of unshipped vehicles will resume from March 4 ).
|
| Kyoto (Oyamazaki) Factory | [Toyota Probox / Mazda Familia Van] Production will resume from February 12, 2024 (shipment of unshipped vehicles will resume from February 5).
|
| Daihatsu Kyushu Co., Ltd. Oita (Nakatsu) 1st Plant/2nd Plant |
[Daihatsu Mira e:S, Hijet Truck, Hijet Cargo, Atrai (including OEM vehicles)] Production will resume from February 26, 2024 (shipment of unshipped vehicles will resume from February 19). [Other models] Operation suspension extended until March 15, 2024. |
| Head Office (Ikeda) Factory Copen Factory | [All vehicles] Operation suspension extended until March 15, 2024 |
Daihatsu news release